Preparing the Next Invoice



After you receive payment for the last invoice or are otherwise ready to prepare the next invoice, first,
Update the last invoice and then follow the procedure outlined below.

 




This Period - Column E


You may enter your new billing information by increasing the percentage (%) for the billing item or by entering the "This Period" dollar amount. When the percentage or dollar amount is entered, press "Enter" to record the information. The edit box will remain on the item allowing you to edit it again if necessary. If it is OK, press "Enter" again to move to the next column. If you press the "Tab" key, the edit box will move to the next column immediately.



Material Stored - Column F


To transfer "Material Stored" to "Column E" or add "Material Stored" to "Column F", move to "Column F" and "Double click" or press the "M" key and the following screen will appear.





To transfer all or a part of the material stored amount to "Column E", enter the desired amount in the appropriate box and press "Enter" the changes will be reflected in the boxes on the "Material Stored Processing" screen. When done, click "Ok".

To add "Material Stored" to Column F, enter the amount in the appropriate box and press "Enter", the changes will be reflected in the boxes on the "Material Stored Processing" screen. When done, click "Ok".

You may edit or reverse the material stored amount by manipulating the values using the "Material Stored Processing" screen. To move a value back into "Material Stored" from "Column E", place a negative (-) value in the "Amount to Transfer to:" box and press "Enter". The amount entered will be subtracted from "Column E" and added back to "Column F". To reduce the value of material stored, without transferring it, place a negative (-) value in the "Amount to Add to Material Stored" box and press "Enter". The amount entered will be subtracted from "Column F".



Retainage - Column I


At this point "Retainage" may be adjusted, if necessary. If no adjustments are necessary, the "Retainage" amount will be computed automatically when you enter your billing values.

You may adjust "Retainage" by billing item, If (although unusual) you have different percentages on various billing Items. to accomplish this, enter the desired percentage in the "%Ret" column. The retainage amount will be adjusted automatically.

If you are setting "Retainage" for the entire Invoice, click the "%Ret" button on the top of the screen to set or reduce the overall retainage percent.



Check the Invoice


This completes preparation of the Invoice, proceed to "Process Invoice" to "View" and or "Print" the invoice.



WB01569_.gif (193 bytes) Leave Manual

 


Copyright 1998-2010 by Computer System Consultants, Inc., Front Royal, Virginia. All Rights Reserved

Phone: 540-635-2100, Fax: 540-635-2140

*AIA Documents G701, G702 and G703 are Copyrighted by The American Institute of Architects, Washington, D.C.

If you have questions or comments about this web site 
mailto: bob@cscisoftware.com

Hit Counter Visitors to CSCI