Retainage



Set Retainage

Retainage may be set

1. Individually by "Billing Item" when you Create New Billing Items.
2. By clicking on "%Ret" while in "Prepare Next Invoice".
3. Individually by "Billing Item", at any time, in Prepare Next Invoice.


Fixed Retainage

After 50% of work, with no additional accumulation

If, for example, retainage was withheld at 10% for the first half of the contract and you now can stop accumulation of additional retainage while maintaining the fixed amount accumulated in the first half of the job. To accomplish this, do the following:

1. Create a "Retainage Billing Item", with a retainage Value equal to the retainage accumulated in the first half of the contract. The "Retainage Billing Item" is created in "Create/Modify Billing Items", by assigning any available item number to the retainage billing item (usually a number that will place it at the bottom of the Invoice). The first nine characters in the "Description of Work" must be "Retainage", in upper or lower case. After the "Description of work" is entered, press "Enter" and the cursor will move automatically to the retainage amount column. Place the retainage amount in the column. Press "Enter" and then press the "Up Arrow" to move off of the new item.

2. Click "%Ret" while in "Prepare Next Invoice", set the retainage to "0" and click "Ok".


After 50% of the work, with additional accumulation

If for example, retainage was withheld at 10% for the first half of the contract and you can now reduce the retainage withheld to 5%. To accomplish this, do the following:

1. Create a "Retainage Billing Item", with a retainage value equal to one half (1/2) of the retainage accumulated in the first half of the contract. The "Retainage Billing Item" is created in "Create/Modify Billing Items", by assigning any available item number to the "Retainage Billing Item" (usually a number that will place it at the bottom of the Invoice). The first nine characters in the "Description of Work" must be "Retainage", in upper or lower case. After the "Description of Work" is entered, Press "Enter" and the cursor will move automatically to the "Retainage Amount" column. Place the retainage amount in the column. Press "Enter" and then press the up arrow to move off of the new item.

2. Click "%Ret" while in "Prepare Next Invoice", set the retainage to "5" and click "Ok".


Payment for Retainage

Reduction in Retainage

Overall retainage may be reduced by clicking "%Ret" while in"Prepare Next Invoice". When reduced, payment is automatically requested (on the Invoice being prepared) for the difference between the retainage accumulated at the original percentage and the retainage indicated by the new retainage percentage.

At the end of the job, to request payment for all accumulated retainage, click "%Ret" while in "Prepare Next Invoice", set the retainage to "0" and click "Ok".

Although unlikely, retainage may be reduced by individual billing item while in the "Prepare Next Invoice" screen. If done, payment will be requested for the difference in the billing item retainage as stated in the paragraph above.





WB01569_.gif (193 bytes) Leave Manual

 


Copyright 1998-2010 by Computer System Consultants, Inc., Front Royal, Virginia. All Rights Reserved

Phone: 540-635-2100, Fax: 540-635-2140

*AIA Documents G701, G702 and G703 are Copyrighted by The American Institute of Architects, Washington, D.C.

If you have questions or comments about this web site 
mailto: bob@cscisoftware.com

Hit Counter Visitors to CSCI